Kkula
In S7 1500 Plc I do positioning tasks with techology objects.
In my process I have positioning tasks that have to be started very accurately based on the position of an external encoder.
I wil do the basic logic for the start of the positioning in the preservo task or an OB3x task set at the cycle of preservo.
I already noticed if the logic is in the preservo task and the execution time of that code becomes rather critical towards the available time slice in the preservo task, the plc will go to stop.
If I put that code in an OB3x that has the same cycle time of the preservo an accidental overrun of the time slice will not stop the plc.
Ok so far, but I was wondering, if the OB3x has the same cycle time as the preservo and all code in it is finished completely within the available time for the OB33x, when is this OBx then executed related to preservo - postservo - ob1?
Our flexible community website is a platform that allows users to connect, share information, and collaborate on various topics of interest. The website offers a range of features such as discussion forums, messaging, user profiles, event calendars, and more. Users can customize their experience by creating and joining different groups or communities based on their interests or location. The website is designed to be user-friendly and adaptable to the needs and preferences of our diverse user base. Whether you are looking to network professionally, share hobbies and interests, or simply connect with like-minded individuals, our flexible community website has something for everyone. Join us today and become a part of our thriving online community!